5 Mins

Introduction

Frank Li

5 Mins

General Workday tasks

Frank Li

5 Mins

Project Updates

Everyone

  • Frank & Carolyn:

    • Power board sch done.

    • Get started on layout.

  • Changxu & Watts:

    • eFuse testboard sch done. Currently working on layout.

    • Layout done by tonight.

  • Devin & Dylan:

    • Battery Balancing Board dataflow & power diagram completed. Started schematic.

    • Goal is to finish schematic BEOWD

  • Jacob & Tony:

    • Jacob submitted review for sch.

    • Finished the layout.

  • Ravi:

    • ordered samples of nanofit connectors to test out

    • considering SMD connectors but will look into further when testing SOM (lakshay)

    • env board/breakout should be ordered by EOW

  • Kaden & Bosa:

    • Parts selection complete

    • sch done by end of next workday.

  • Shaun:

    • Got interrupts working on the CubeIDE. Created polling based tests.

    • LHR embedded environment doesn’t have libraries required for some functions.

    • Fix: move the libraries.

5 Mins

Conclusion

 Frank Li