...
Dynamics: | Aeroshell: | Body: | Emech: | |
---|---|---|---|---|
Blockers/Conflicts | Do you have any blockers or conflicts that are preventing you from making forward progress/completing certain tasks OR making things more difficult than they should be? | |||
🚪 🛑 🔒🚫 🚧 🕰️ 👩 | can we make roll cage smaller 🥺 Ansys whitelists? | nah. (yay yippee woooooooo hooo!!!!!!!!) | ||
General Updates | Unsprung:
Suspension:
Steering:
| Battery Box panels completed and ready for waterjetting Finalized shell all but done
| Frame
Ergo
| |
Winter Break Plans | Unsprung:
Suspension: Steering:
| Aerodynamics We (will) have a finalized shell, and break will just be making edits. We could send out the shell now and be done, any edits we make now are for optimization Composites Mold prep testing - Foam and prep materials are ordered so when they arrive i’m gonna test application and processing methods. Goal is to have a clear methodology by end of break so that we are ready for when molds arrive Resin infusion - Initial resin infusion tests, set up; flow distance, just figuring out process. Hopefully we’ll be able to use it for flat panels/small components (maybe if we wanna remake daybreak canopy? idk yet tho) HV Distributuion enclosure manufacturing - Up to when Ajay can come to austin, we’re gonna figure something out Composite frame - Manufacture test pieces for aluminum honeycomb and nomex; test process of application for secondary bonding, finalize shear test fixture (hopefully manufacture that too but thats not something i can do) Start learning simming of composites through ansys mechanical → personal goal for winter break is to have a 4 ply composite face sheet simmed, will add core if I have time Acetone vapor smoothing - Figure it out, may have to remake enclosure for smoothing bc current emech one has leakage issues Composite Pushrods - Buckling calcs, starting with metal so that we can understand how buckling works, and then trying to figure out how buckling for composite tubes works Misc - Resand and refinish the metal sheet; sand another one too just bc we need the work surface for future (Assuming its not too cold to wet sand loll) I think im forgetting something else but honestly cant remember rn | Sim tweak validate, sim tweak validate, etc.
Experiment with composite structural simming Complete Daybreak pedal box Have all Next Gen ergo parts exist in CAD (i.e. have a 1st iteration essentially finished) | HV Distributuion enclosure manufacturing - honestly up to advait if he has time and wants to do it DB dashboard, mppts, mounting for moco. DB Batt pcbs panel waterjet completed |
Daybreak Progress |
| uh | ||
Questions people have | ||||
What do you need from me this week? |
...