Status of Renovations and Maintenance Work

MRH/MBE

Currently, the HVAC electric prep work that was scheduled for the week of Spring Break in MRH and MBE has been canceled. As of today, the abatement work that was happening in MRH basement is still happening next week (just not the power shutdown) and the HVAC will be shutdown Tuesday-Thursday “if Zone is available to shut them down”.

We have no information as to the HVAC work in MBE, originally scheduled for 3/19-3/22 at this time.

...

For DMA Lecture recitals, only the co-supervisors will be required to grade them. For all other recitals, only the main faculty member will need to grade the student.


Last updated on 3/1820/20