  1. All traffic within one department
  2. All traffic from any computer connected to VPN
  3. All outgoing connections from the computer inside PMA except when connecting to a different department in PMA

  4. If you can perform a task while on Wi-Fi you will be able to perform the same task while on hardwire except when connecting to a different department in PMA

  5. Connections to instrument and printer networks

  6. Any whitelisted services (Complete this form to request a service to be whitelisted: https://utexas.qualtrics.com/jfe/form/SV_6Rplgi8pWRUTz9j )

What will no longer work after all the rules are applied (please see graphic below):

...

    • Phase 1: 49152-65535 — Mon 11/16
    • Phase 2: 10000-49151 — Wed 11/18
    • Phase 3: 5000-10000 — Thur 11/19
    • Phase 4: 1024-4999 — Mon 11/23
    • Phase 5: 100-1023 — 11/30-12/3 (few ports a day M-Th - schedule TBD
      • 973-1023 — Mon 11/30
      • 742-972 — Tues 12/1
      • 408-741 — Wed 12/2
      • 100-407 — Thurs 12/3
    • Phase 6: 1-99 — 1/5-1/14 (do a few ports a day M-Th - schedule TBD)

...