4/255/8/2023 – 5/10/2023

1) Facade lintel removed for crane access into NHB patio.

2) Patio paving slabs removed revealing the location of the new access shaft.

3) ) Removal of a beam section from the patio deck. 2) Progress on opening up the access shaft.

3) The final beam is removed from the opening.

4) The approx 13' x 13' access shaft opening is now fully accessible.

Image AddedImage AddedImage AddedImage Added

5/4/2023 – 5/5/2023

1), Scaffolding in place to support the NHB patio prior to creating the access opening.

2) Saw-cutting of the patio deck to open up the shaft.

3) Daylight now visible from the drop-zone in the basement !!

Image AddedImage AddedImage Added

5/3/2023 – 5/4/2023

1) Excavation underneath NHB to reach limestone bedrock for the footings that will support the access shaft superstructure.

2) Rebar cage component of the footing. 3) Rebar cage in place, ready for the concrete pour

Image AddedImage AddedImage Added

4/25/2023

1) Facade lintel removed for crane access into NHB patio.

2) Relocation of HVAC ductwork and piping in the mezzanine level to clear the shaft drop-zone.

3), 4) Patio paving slabs removed revealing the location of the new access shaft.

...

4/11/2023

1), 2) Excavation for the footings that will support the removable patio slab

...