5/19/2023
1) NHB access shaft from below, ready for the Skyra to be rigged out of the basement MRI suite
2) Trucks arrayed down Speedway
3), 4) The crane arrives and is ready for action.
5) Timelapse and 6) video as the Skyra MRI is hoisted out of the NHB basement.
6) Skyra MRI suspended above E 24th St, and 7) lowered onto its struck
8) Farewell Skyra.
View file | ||||
---|---|---|---|---|
|
...
5/8/2023 – 5/10/2023
1) Removal of a beam section from the patio deck. 2) Progress on opening up the access shaft.
...
3) Daylight now visible from the drop-zone in the basement !!
...
5/3/2023 – 5/4/2023
1) Excavation underneath NHB to reach limestone bedrock for the footings that will support the access shaft superstructure.
2) Rebar cage component of the footing. 3) Rebar cage in place, ready for the concrete pour
...