4/25/2023

1) Facade lintel removed for crane access into NHB patio.

2) Patio paving slabs removed revealing the location of the new access shaft.

3) Relocation of HVAC ductwork and piping in the mezzanine level to clear the shaft drop-zone.


4/11/2023

1), 2) Excavation for the footings that will support the removable patio slab

3) Demo of the former TMS lab and conference room - location of the new drop-zone for the MRI. 


3/27/2023

1) Demo of the former TMS lab and conference room


3/20/2023

1) Ramp-down of the 3T Skyra MRI initiated - ending 11+ years of service for the IRC/BIC

2) Initial demo of the former BIC Conference Room


3/13/2023