  1. After moving IGRINS to the 6th floor connect the A/B/C cables for the pressure gauge and temperature sensors.
  2. The fiber optic network cable must be connected so the instrument can be monitored remotely.
  3. Do not:   
    1. Connect detector power and USB unless requested.
    2. Connect the Calibration Unit cables unless requested.
    3. Press the power button on the three black Windows computers in the electronics cabinet.
  4. The Lakeshore heaters should be set to normal operating temperatures.   
  5. The first three buttons on the EATON power supply, controlling the power to the calibration lamps, need to be turned off.
  6. Housekeeping Package should be started and verified with Greg or Hwi.
  7.  Note:
    1. Large jolts and impacts can harm the optics and the detectors are sensitive to power fluctuations.        
    2. As part of Fduty please ensure that heaters are operating normally, that the dewar pressure is lower than 1E-7 torr, and that the CTI Coldhead is making the appropriate maraca noises.

...

  1. It will take IGRINS ~2 days to warm to room temperature, 3 days to pump, and another 3 days to cool back to operating temperature. 
  2. After moving IGRINS to the 6th floor connect the A/B/C cables for the pressure gauge and temperature sensors.
  3. The fiber optic network cable must be connected so the instrument can be monitored remotely.
  4. Do not:  
    1. Connect detector power and USB unless requested. 
    2. Connect the Calibration Unit cables unless requested.
    3. Press the power button on the three black Windows computers in the electronics cabinet.
  5. The first three buttons on the EATON power supply, controlling the power to the calibration lamps, need to be turned off.
  6. Housekeeping Package should be started and verified with Greg or Hwi.
  7. Read the Vacuum Refresh Procedure before starting this process.
  8. Note:
    1. While warm, IGRINS detectors are at risk of deteriorating when exposed to temperatures above 100F. The refrigerated dome is safe, but outside is not.
    2. As part of Fduty please ensure that the Lakeshore heaters are set to normal operating temperatures, that the dewar pressure is lower than 1E-7 torr, and that the CTI Coldhead is making the appropriate maraca noises.