Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Attendees

Goals

Discussion Agenda

Time

Item

Who

Notes

 

Old Action Items

Pratyush Patra

  • Action items-

    • Dacq Review November 9th

 

Workday/Review Takeaways

 

 

Workday

 

Workday

  • BPS

  • Pablo

    • Donezo with projects

    • Adhiv and Aayush- Leaderboard documentation for XBee

    • Victoria and Amanda- Pychrono documentation

    • Matthew- Chugging along on Leaderboard

    • Jim- UART done

    • Lance- Doing things

  • Diya(Go up to pickle)

    • Oscar- Big motor documentation

    • Eliana- Pedal Board, Requirements

    • Mika- Daybreak dashboard, PR open, dialed

    • Lucy- Working on lighting board, reqs done before workday, Start schematic

    • Maddie, Krish- Check if schematic finished

    • Jiwoo and Arnav- Continuing FSM work

    • Akshay- Figure out if that camera actually works

  • Frank the Tank Li

    • Carolyn and Frank- Open PRRRRRRFRRR

    • Changxu and Watts- Changing the E-Fuse

    • Jacob and Tony- Good HV design research

    • Ravi- Schematic needs review

    • Twins- Contactor driver done

    • Shaun- I2C BSP done maybe, interrupts

  • Andrew

    • Tanya- I2C testing with Motor

    • Tong- Working with Advaith on cooling stuff, Getting PCB done

    • Aarav- BSP_ADC, Making good progress

    • Erika, Aleena, Isaac- Wrote documentation, Gonna order voltage and current board

    • Praneel- Sick

    • Nikhil- Sim PV

    • Roy- Web socket(422C) for Eclipse 0.4, HLS sux

    • Nash- Got Matthew’s algo working

    • Andrew- Talk to members, Talk to Prat

 

Timeline Check-in

 

  • Boards done?

    • BPS-

      • Abigail and Clark on track, Pushing for scheme done EOD

      • Nathan on track for December

    • Pablo-

      • Ravi- Needs review

      • Talk to Matthew

      • Adiv and Aayush

    • Frank-

      • Precharge- Needs review

      • Power Board- Review by EOD

      • EFuse breakout board

    • Diya-

      • Leader Rework- Should be on track

      • Lighting board- Talk to Lucy to clear up some conceptual questions

      • Pedal board- Eliana making good progress

      • Dashboard- Mika picked out components

    • Andrew

      • MPPT- Talk about the timeline

      • Blackbody-

  • BSP done?

    • UART- Interrupt driven test

    • SPI- Behind needs testing

    • ADC- Pretty on track

    • CAN- Silly little things

    • I2C- Interrupt driven test

 

Purchasing

 

  • Mouser- Connectors and Contactor Driver equipment

  • XBee

  • Diya will send things

Drive Day

Discussion Notes

  • Action items-

    • November 9th DAcq review

    • Talk about MPPT timeline