| Dynamics: | Aeroshell: | Body: | Emech: |
---|
Blockers | It was brought to my attention that some people are having a difficult time knowing where/how to start since some design/architecture decisions haven’t been made yet. What are y’all having trouble with? |
| | | 26 regs for battery capacity battery location (front, back, split?)
|
Workday Review | Suspension: Steering: Unsprung: | Composites Aerodynamics | Frame: Talked with suspension for clarification on what rear trailing arm and double wishbone approaches look like for frame Also got together an approach for designing around hardpoints and making reference sketches Frame Parameters spreadsheet created
Ergo: | High level electrical schematic finally exists for daybreak Intake and Exhausts for daybreak new battery started (with new enclosure) Cooling Calcs for heat disspication - currently looking for thermal mass/amount of lithium inside of cells to get a numerical value. We have it symbolically solved Once we know heat generation, we can move onto dissipication efficiency of different solutions
|
Next Workday Plan | General: Suspension: Steering: Unsprung: | Composites Finish array test panels, finalize initial tests, order materials, and start some of the work on daybreak
Aerodynamics | Frame: Go over general statics/solids intuition as applied to frame building Continue determining general roll cage dimensions and creating frame reference sketch Create varying designs for front and rear of chassis (new member task)
Ergo: Review and then manufacture the pedal jig → Finish measuring drivers Continue adapting percy model with survey data and eventually measured data Generate a preliminary steering wheel design/manufacturing method Continue brake calcs
| Wire Harnessing - Do a more in-depth lecture with final details, signalling, etc for daybreak and come up with possible solutions for placement and topology Cooling - complete exhausts and intakes on battery and keep working on finding and calculating values we need and create a “database” of values we are finding Try to do waterproofing testing for univ enclosure get a design done for vapor smoothing chamber and start ordering parts eod
|
Daybreak Progress? | - New Suspension Geometry - due Yesterday
- New Wishbone Model - due Yesterday
- Select Spherical Bearings - due two days ago
- Bearing Mounting Scheme - due Yesterday
- Bearing Mounting Design - due Yesterday
| - Progress on Refinishing bottom shell?
| | - When are battery materials getting ordered
|
Questions people want to ask: | | | | |
What do you need from me this week? | | | | |