7/14/2023
1) The 3T Prisma system installed just prior to ramp to field.
2) Finish-out of the Center beneath the access shaft drop-zone currently in progress.
3) Paving stones have been re-laid on the NHB patio, covering the location of the access shaft.
...
6/4/2023
1) The 3T Prisma system arrives on campus.
...