\uD83D\uDC65 Attendance

  • Michael Mohn
  • Philip Bortolotti
  • Hardhik Sripuram
  • Gerard Cardenas
  • Pratyush Patra
  • Diya Rajon
  • Lakshay Gupta
  • Andrew Yin
  • Pablo Romero
  • Frank Li
  • Parthiv Shah
  • Noah Hickman
  • Harshit Dalmia
  • Jason Heston

📝 General Updates

  • General Meeting at 7:30 this Thursday in ECJ 1.202. React for Cabo Bob’s

  • Facilities updates

    • Laser Cutter has been removed from the ETC Garage. This gives us a much larger working footprint. Solar could try to negotiate for some of that space for frame welding purposes

    • Walt cleared out the flammable cabinet in the engine room

  • Would people be interested in a pre-thanksgiving or pre-winter break movie night/karaoke? Philip will send a message out tomorrow gauging member interest.

\uD83E\uDD45 Goals

  • Get updates from leads


💸 Operations

  • Any tire updates?

🛠️ Chief Engineer

  • Chief Engineer Feedback Form

    • https://forms.gle/WxBK1oPsaaH5T1fQ7

    • I will check this on a weekly basis. It is anonymous, so please fill out if you have anything you want to tell me, especially if it is criticism

  • Projects I am working on this week

    • Creating dynamics reference sketch with displacements

    • Modeling Instron testing fixtures for composites

  • Cheefy Help Zone

    • Are there any projects y’all would like my help on

  • Areas of Interest

    • Array x Aeroshell layout discussion progress?


\uD83D\uDDE3 System Updates

🚨 Controls:

Updates

  • Motor Controller STILL isn’t working (no more CAN Issues tho)

    • Parthiv can say more abt this

    • Don’t think this is from Controls side, need to verify.

  • Three more members know how to use profinity/set up + debug

  • Maddie and Krish - Layout in progress

  • Lucy - Lighting schematic draft reviewed

  • Oscar - Leader Dash, SendTriitum

  • Mika - Addressing Parthiv’s ideas on dashboard, addressing pedals board accel sensor

Week Plan

  • meeting with Eliana Thursday to look at brakeline for board

  • I intend to stay on campus throughout break to catch up on whatever work is behind (after 5 PM everyday): pedals board, MC fix if possible, ordering, finalizing with dash etc.

Upcoming Deadlines

Pedal needs to have first draft completed EOW.

🔥 BPS:

Updates

  •  

Week Plan

 

Upcoming Deadlines

⚡ Power Generation:

Updates

  • MPPT ADC breakout board review

  • Starting MPPT fw makefiles

  • Array layout w/ Jason

  • Temp and Irradiance sense board schematic start

  • constant current driver re make schematic

  • PV capture database implementation complete; continuing database manager

  • training loop for model works :DD

Week Plan

  • finish up array layout w/ jason & send it to d2

Upcoming Deadlines

📻 Data Acquisition:

Updates

  • Weather + Array + Battery + Terrain all integrated. Working on simulating dynamics.

  • RF Receiver schematic complete. Working on layout

  • IMU/RPM board schematic complete. Working on layout.

Week Plan

  • Give thanks to the people that have given us so much

Upcoming Deadlines

- RF Board Layout

- IMU/RPM Board Layout

🔋 Power Systems:

Updates

  • Power board layout complete. Waiting on review. Reviews will be addresed prior to thanksgiving break and ordered by the same deadline.

  • Contactor driver and dataacq env board ordered.

  • eFuse testboard ready for review. Will be ordered alongside power board

  • Good progress on env board software (reading humidity and temp values on terminal).

  • Active precharge board undergoing a slight change (changing power delivery from LDO to buck). Finished and awaiting review.

  • Power monitoring board sch reviewed. Layout will start soon.

  • Encountered some issues when trying to spotweld on sigmaclad. Reached out to Kevin Yu (electric) with observations and questions. Havent recieved a response just yet.

Week Plan

  • Continue battery manufacturing (spotwelding) testing

  • review active precharge and eFuse testboard.

  • We also try out hand at the challenges placed before us. But we do it better. 😎

 

Upcoming Deadlines

  • - Power Board Layout
  • - Order Power Board
  • - Order eFuse testboard
  • - ESP32 Batt Char board sch
  • - Power Mon board layout
  • - Active Precharge layout

🔌 Electromechanical:

Updates

  • critical hardware back in car and harnessed

  • mock cooling intake done to send to regs

  • ready to manufacture mock modules

  • start characterization of a few cells with ps

Week Plan

  • have all battery box panel cutouts finished and dxfs created for waterjet

    • only layups will be a blocker then

 

 

Upcoming Deadlines

  • EOD Sat - BB waterjet files

🧑‍🏭 Body:

Updates

  • Frame 1st iteration had to be redone

  • Jig Design plan and Welding order started

  • Pedal Jig used, pedal ratio was tested and confirmed for daybreak pedal box redesign

  • Steering Wheel layup setup tested, CFC viable for steering wheel construction, needs some refinement

Week Plan

  • Go over welding theory to help with jigging/welding plan

  • Re-finish 1st frame iteration, start ansys sims

  • Decide pedal box placement/bounding box

  • Continue work on Daybreak pedal box redesign

 

Upcoming Deadlines

  • Nov 16, 2024 - Roll cage position/dimensions set
  • Nov 16, 2024 - Driver Model finalized
  •  

🔩 Dynamics:

Updates

  • General:

    • Manufactured inserts for composites testing

  • Unsprung:

    • Decided brakes

    • CAD for rear a-arm structure

  • Suspension:

    • Talked with fergo to better understand bounding boxes and HDPTS need to be changed

    • All members got Ansys installed

    • Carter is doing finding the loads related to bell cranks

    • Oliver and La’akea began learning manufacturing with me and Gerard

  • Steering:

    • Found lower steering rack geometry

 

Week Plan

  • Unsprung:

    • More mockup designs for both front and rear

    • Break button dimensions and forces on the rotor when we lock up

  • Suspension:

    • First iteration rear reference sketch

    • Load conditions for suspension focusing on bell cranks

    • Oliver and La’akea testing pushrods

    • Test with dummy suspension

  • Steering:

    • Reviewing lower steering rack geometry

    • Members work on designs for upper steering, figuring out how gearbox will work

 

Upcoming Deadlines

  • - Brake calipers and rotor size decided (Arav needs to get us this data) - Unsprung
  • - Axle length (already have somewhat of an idea) – switched to doing sims instead - Unsprung
  • - Upper steering architecture selected (is in talks with ergo and suspension)- Steering
  • - Bump steer design optimization - Steering
  • - Version 1 of Upright design in CAD - Unsprung
  • - Finalize brakes and rotor config (Arav needs to get us this data) - Unsprung
  • - Caliper and motor mount for Swingarm - Unsprung + Suspension
  • - Decide bearings - Unspung
  • - Version 1 of Hub design in CAD - Unsprung
  • - Suspension Geometry Finalized - Suspension

💨 Aeroshell:

Updates

  • Aerodynamics

    • Members have been taught ANSYS

  • Composites

    • Battery box layup, worked on resin infusion research and test fixtures for composite panels

 

Week Plan

  • Aerodynamics

    • Everyone have a sim done of the parts that they have made by next workday

    • Getting into the flow of make variation, sim variation

  • Composites

    • Battery box, first frame panel test subject, maybe machining test fixtures (not sure on this yet, depends on materials), design molds for wire cutter

 

Upcoming Deadlines

  • Nov 16. 2024 - all members have run sim

✅ Action items

  •  

⤴ Decisions