Time | Item | Who | Notes |
---|
| Old Action Items | Pratyush Patra | Action items- Talk to Philip about mechanical data reqs(Done) Talk to Matthew about Leader schematic progress(Done) Talk about lighting and pedal(To do) Figure out Controls Leader Rework review status(Added lights stuff) Jim Talk to Erika, Aleena, and Isaac Talk about op amp mosfet stuff(Done)
|
| Workday/Review Takeaways | | Motor work! Design Review Takeaways Isolation not necessary for all the buses Still isolate peripheral gnd Characterize CAN bandwidth Keeping contactors New DCDC, New Supp Fuse upstream CAN DBC
| |
| Workday | | Workday BPS Kadhir- CAN loopback working Abigail- Schematic for the board Phoenix- PWM working on HAL, fix interrupt issues Nathan- Found some new components Clark- New ADC Aneri- Needs to finish SPI stuff Kartik- Michael- Makefileeeeeeee
Pablo Donezo with projects Adhiv and Aayush- Leaderboard documentation for XBee Victoria and Amanda- Pychrono documentation Matthew- Chugging along on Leaderboard Jim- UART done Lance- Doing things
Diya(Go up to pickle) Oscar- Big motor documentation Eliana- Pedal Board, Requirements Mika- Daybreak dashboard, PR open, dialed Lucy- Working on lighting board, reqs done before workday, Start schematic Maddie, Krish- Check if schematic finished Jiwoo and Arnav- Continuing FSM work Akshay- Figure out if that camera actually works
Frank the Tank Li Carolyn and Frank- Open PRRRRRRFRRR Changxu and Watts- Changing the E-Fuse Jacob and Tony- Good HV design research Ravi- Schematic needs review Twins- Contactor driver done Shaun- I2C BSP done maybe, interrupts
Andrew Tanya- I2C testing with Motor Tong- Working with Advaith on cooling stuff, Getting PCB done Aarav- BSP_ADC, Making good progress Erika, Aleena, Isaac- Wrote documentation, Gonna order voltage and current board Praneel- Sick Nikhil- Sim PV Roy- Web socket(422C) for Eclipse 0.4, HLS sux Nash- Got Matthew’s algo working Andrew- Talk to members, Talk to Prat
|
| Timeline Check-in | | Boards done? BPS- Pablo- Ravi- Needs review Talk to Matthew Adiv and Aayush
Frank- Diya- Leader Rework- Should be on track Lighting board- Talk to Lucy to clear up some conceptual questions Pedal board- Eliana making good progress Dashboard- Mika picked out components
Andrew
BSP done? UART- Interrupt driven test SPI- Behind needs testing ADC- Pretty on track CAN- Silly little things I2C- Interrupt driven test
|
| Purchasing | | |
| Drive Day | | |