Attendees

Goals

Discussion Agenda

Time

Item

Who

Notes

 

Old Action Items

Pratyush Patra

  • Action items-

    • Talk to Philip about mechanical data reqs(Done)

    • Talk to Matthew about Leader schematic progress(Done)

    • Talk about lighting and pedal(To do)

    • Figure out Controls Leader Rework review status(Added lights stuff)

    • Jim

    • Talk to Erika, Aleena, and Isaac

    • Talk about op amp mosfet stuff(Done)

 

Workday/Review Takeaways

 

  • Motor work!

  • Design Review Takeaways

    • Isolation not necessary for all the buses

    • Still isolate peripheral gnd

    • Characterize CAN bandwidth

    • Keeping contactors

    • New DCDC, New Supp

    • Fuse upstream

    • CAN DBC

 

Workday

 

Workday

  • BPS

    • Kadhir- CAN loopback working

    • Abigail- Schematic for the board

    • Phoenix- PWM working on HAL, fix interrupt issues

    • Nathan- Found some new components

    • Clark- New ADC

    • Aneri- Needs to finish SPI stuff

    • Kartik-

    • Michael- Makefileeeeeeee

  • Pablo

    • Donezo with projects

    • Adhiv and Aayush- Leaderboard documentation for XBee

    • Victoria and Amanda- Pychrono documentation

    • Matthew- Chugging along on Leaderboard

    • Jim- UART done

    • Lance- Doing things

  • Diya(Go up to pickle)

    • Oscar- Big motor documentation

    • Eliana- Pedal Board, Requirements

    • Mika- Daybreak dashboard, PR open, dialed

    • Lucy- Working on lighting board, reqs done before workday, Start schematic

    • Maddie, Krish- Check if schematic finished

    • Jiwoo and Arnav- Continuing FSM work

    • Akshay- Figure out if that camera actually works

  • Frank the Tank Li

    • Carolyn and Frank- Open PRRRRRRFRRR

    • Changxu and Watts- Changing the E-Fuse

    • Jacob and Tony- Good HV design research

    • Ravi- Schematic needs review

    • Twins- Contactor driver done

    • Shaun- I2C BSP done maybe, interrupts

  • Andrew

    • Tanya- I2C testing with Motor

    • Tong- Working with Advaith on cooling stuff, Getting PCB done

    • Aarav- BSP_ADC, Making good progress

    • Erika, Aleena, Isaac- Wrote documentation, Gonna order voltage and current board

    • Praneel- Sick

    • Nikhil- Sim PV

    • Roy- Web socket(422C) for Eclipse 0.4, HLS sux

    • Nash- Got Matthew’s algo working

    • Andrew- Talk to members, Talk to Prat

 

Timeline Check-in

 

  •  

 

Purchasing

 

  • MPPTs check in

  • XBee check in

  • Buy component organizers

  • Mouser OPS goated

  • Figuring out JLCPCB stuff

  • Find oscilloscope

Discussion Notes

  • Action items-

    • November 9th DAcq review