The information provided here is intended to augment existing information on the SoHE wiki’s “purchasing” section and HBP 12.3.

Before work can commence, please follow these steps and allow for two weeks processing time:

  1. Ask Erin Machell to verify and/or create a vendor ID

  2. With the vendor’s ID, PI will complete the EICC form to determine that this is

    independent contract work. This must be done every time you hire an independent

    contractor, even if you’ve hired that person before.

  3. PI requests a quote or contract for the work from the vendor that describes the

    work.

  4. Email the required paperwork(the EICCC form, Quote and a Purchase Request

    Form) to business services to review and finalize the pre- approval to hire the vendor.

...