\uD83D\uDDD3 Date
\uD83E\uDD45 Goals
Complete High-Level Timeline
Have a discussion about the new regs and what they mean for our team
💸 Operations
🛠️ Chief Engineer
We have four workdays left in this semester
\uD83D\uDDE3 System Updates
🚨 Controls:
Updates
Lucy - Lighting schematic in progress
Eliana - Worked on finding datasheet and connector info for the desired pedal sensor. Current selection might not be used. Completed brakeline portion of the schematic. Pushed her current progress
Maddie & Krish - Pushed schematic deadline to Nov 14th. Review required. Thanks Lakshay and Prat for leaving reviews!
Mika - Selected inputs sensors for dashboard. need to order
Akshay - Display is chosen, camera in progress. Blocked because current choice wasn’t waterproofed (mb)
Oscar - given controls leader-daughter which is comprised of dashboard
Second half of workday - tested motor noise on array (woop woop Ikococator)
Week Plan
Order display, cameras, lights, compute module
Upcoming Deadlines
- - Leader rework order
🔥 BPS:
Updates
Michael (the cooler one) got his first PR merged in!
Fan board, Scrutineering, and PSOM are all in
Most soldering and testing is going to have to happen outside of workday
Starting dev on some test boards
Admittedly, there is not as much work progress on boards as I’d like
Clark and Abby are making good progress on their boards
Pheonix was blocked for a bit by a Lakshay skill issue but is doing well in her project and is moving pretty fast
Michael is starting work on our watchdog
Week Plan
BPS members are getting a soldering showcase from Champers during workday
I will also be doing a talk on ✨ reading datasheets ✨
Upcoming Deadlines
- - Deadline
⚡ Power Generation:
Updates
Updates Go Here
Week Plan
Updates Go Here
Upcoming Deadlines
- - Deadline
📻 Data Acquisition:
Updates
Updates Go Here
Week Plan
Updates Go Here
Upcoming Deadlines
- - Deadline
🔋 Power Systems:
Updates
Power board schematic finished! good for review
Watts and Changxu almost done with an eFuse testboard schematic.
Shaun got polling test done for I2C BSP. Now working on interrupt based test.
Devin and Dylan finished contactor driver!!!!! Also finished high level block diagram of batt characterization board.
Jacob and Tony went through a bunch of edge cases with the Active Precharge board. Did a bunch of considerations into potential current pathways, floating nodes, etc.
Ravi still working on environmental board layout after several changes. Changes include creating a breakout board for humidity, temp, and airflow sensor. Currently trying to find a connector with a smaller form factor as per emech’s request.
Bosa and Kaden found a power monitoring chip for power monitoring board.
Week Plan
order contactor driver and (potentially) eFuse testboard
order mouser components
get power board reviewed and start layout
Upcoming Deadlines
- - Deadline
🔌 Electromechanical:
Updates
starting battery manufacturing
Week Plan
order hardware and aluminum
assemble universal enclosure and do water test workday
Upcoming Deadlines
- - Deadline
🧑🏭 Body:
Updates
Updates Go Here
Week Plan
Updates Go Here
Upcoming Deadlines
- - Deadline
🔩 Dynamics:
Updates
Updates Go Here
Week Plan
Updates Go Here
Upcoming Deadlines
- - Deadline
💨 Aeroshell:
Updates
Aero Dependencies Chart
We selected who is working on different projects
We have someone for shell to shell and canopy tilting
Week Plan
Jason and Aidan need to make reference sketches and two starter shells b4 next workday
Upcoming Deadlines
- - Deadline