Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 12 Current »

\uD83D\uDC65 Attendance

  • Michael Mohn
  • Philip Bortolotti
  • Hardhik Sripuram
  • Gerard Cardenas
  • Pratyush Patra
  • Diya Rajon
  • Lakshay Gupta
  • Andrew Yin
  • Pablo Romero
  • Frank Li
  • Parthiv Shah
  • Noah Hickman
  • Harshit Dalmia
  • Jason Heston

📝 General Updates

  • Come to elections

  • submit pr’s please

  • we should do a movie night this weekend

  • we only got slightly shit on in pvdr

  • winter gala probably not happening

  • how are 1-on-1’s going

  • pickle is dirty :(

💸 Operations

Updates

CR

  • Annika

    • working on getting the oscilloscopes (need purchase update from y’all)

    • tentative ship date for the transducers is 12/12

  • Niloo

    • Working on cowtown materials for massive foam blocks

    • still on the hunt for solar cells and stuff (need some responses from Andrew)

    • Working on smaller foam machiners

  • Arav

    • brakes and stuff, not much from him yet

  • Jackson

    • Mainly monetary right now

PR

  • Big things to come with ePlan

    • bi-weekly videos with their production team for mini-series

    • USA President and Global President slated to attend unveiling

      • hopeful unveiling partners

    • We need to begin using the software so that we can get into using the stuff for videos

      • these videos will be on ePlan website and socials and we can use as well

      • PR team will begin working on this starting our workday

Workday Plan

  • Begin teaching the team about new outreach software Jackson found

  • Practice pitches and cold calls

  • Final call for systems to give requests before break

  • Work with teams to finalize plans for merch and new opportunities to come next sem

🛠️ Chief Engineer

✅ Previous Action items

  • Andrew gonna motivate (smile)
  • i wanna talk with aeroshell
  • i wanna talk with gerard/diya/parthy
  • power gen new lead
  • Rectangular vs Curved top shell FEA done by workday

\uD83D\uDDE3 System Updates

🚨 Controls:

Updates

  • Maddie and Krish - routing is in progress and almost complete

  • Mika - finished dash routing. review needed.

  • Oscar - Leader Dash, SendTriitum

  • Eliana - Busy, started on pedals board schematic.

  • Lucy - Busy. Lighting schematic needed to be updated

  • Akshay - started on schematic for the breakout board

Week Plan

  • wanna go to pickle to test motor stuff. i can’t go in until friday. maybe have another member go in with Parthiv.

  • one on ones (next week)

Upcoming Deadlines

  • didn’t get much progress over break as I wanted.

  • Controls Software Architecture

  • Motor controller -

🔥 BPS:

Updates

  • No progress on Watchdog from Michael over break. I’m helping him with some errors he has in there.

  • Phoenix is integrating the PWM code she’s writing into some other code that was recently written.

  • Clark starting layout

  • Abby is also starting layout

  • Goal for Amperes is reviewable schematic by end of workday but I expect that to be pushed a weekish

  • I doubt boards will be ready by winter break, talking to my members they said they could work on it during break.

Week Plan

  •  

Upcoming Deadlines:

  • [in review ]- 11/09/26 - BPS Leader Software Architecture

  • [In review] PeripheralSOM

  • 11/23/26 - IWDG with HAL and no RTOS

 

⚡ Power Generation:

Updates

  • Commercial MPPT arrived :0

  • Tanya

    • should we daisy chain or web blackbody Cs?

    • gonna have a separate irradiance board from blackbody C to extend to top shell

  • There’s issues with rectangle topshell

  • MPPT group

    • moving on to researching boost converter

    • waiting for champer’s final review of schematics

  • Tong

    • Schematics for lighting. Should be ready for review this weekend.

Week Plan

  •  Need to fill out some forms for solar cells for Niloo

  • Did operations reach out to make-my-solar? Can’t remember if I’ve done the forms yet.

 

Upcoming Deadlines

  • 12/9/2024 - Array Layout Sent to D2 for review

  • 12/16/2024 - Order boards

  • 01/19/2024 - Array x Mechanical PDR

 

📻 Data Acquisition:

Updates

  • Weather + Array + Battery + Terrain all integrated. Working on simulating dynamics.

  • RF Receiver schematic complete. Working on layout

  • IMU/RPM board schematic complete. Working on layout.

Week Plan

  • Give thanks to the people that have given us so much

Upcoming Deadlines

- RF Board Layout

- IMU/RPM Board Layout

 

🔋 Power Systems:

Updates

  • Power board ordered!

  • eFuse testboard reviewed. Yet to be ordered

  • Active precharge board (hardware version) ordered and received! Jacob is testing LV side.

  • Power monitoring board layout started.

  • No waterjetted sigma clad yet. Might need to do some spot-welding over break.

Week Plan

  • push for board finalization and get most (if not all) current-gen and test boards ordered soon.

 

Upcoming Deadlines

  • - Power Board Layout
  • - Order Power Board
  • - Order eFuse testboard
  • - ESP32 Batt Char board sch
  • - Power Mon board layout
  • - Active Precharge layout

🔌 Electromechanical:

Updates

  • eplan licenses acquired

  • moco cooling complete

  • Intake/exhaust panel patterns

Week Plan

  • replace motor fuse, try to run again

  • finish battery panels and send them to get water jet

  • start manufacturing new battery locks

  • start manufacturing vibration jig

  • cooling stuff - intake, exhaust, mppt, calcs

 

Upcoming Deadlines

  • Dec 4 - MPPT and MoCo Enclosures

 

🧑‍🏭 Body:

Updates

  • Completed some initial Ansys sims (had errors with meshing, currently working on it)

  • Work done on daybreak pedal box (to be finished soon)

  • yeah lol it was break

Week Plan

  • Finish simming latest frame iteration

  • Compile next steps for changing frame design

  • Continue work on Daybreak pedal box redesign

  • Finish up initial CAD designs for next-gen steering wheel, ballast box, and daybreak steering wheel

 

Upcoming Deadlines

  • Dec 14th, 2024 - Finish welding plan and initial frame jig design plan
  • Dec 14th, 2024 - Initial Ergo CAD designs finished

🔩 Dynamics:

Updates

  • General:

    • Slept and traveled not much work done

  • Unsprung:

    • Unsprung was traveling the entire time

  • Suspension:

    • Suspension got a mix of some CAD and force matrix but also some weren’t able to get work done.

  • Steering:

    • Steering got upper and lower steering CAD to exist

 

Week Plan

  • CAD for every part should exist by Thursday

  • Unsprung:

    • Sim the hubs

      • Redesign

    • Break button dimensions and forces on the rotor when we lock up

    • Figure out how to properly use SKF simquick pro

    • Finalize brake rotor design, figure out ways to manufacture in house or outsource the manufacturing of the brake rotors, and document your brake rotor decision process

    • Make CAD for trailing arm with caliper mount, motor joint, and “pin joint” for the frame

  • Suspension:

    • completely define the hdpts

    • first sim dummy apexes and bellcranks

    • define spring rates ( have to talk to ic and fix some orientations of the masses on the car maybe)

    • probably going to tweak the motion ratio in the front - first shock selections

  • Steering:

    • Talk to Kenta about actual location of upper steering pertaining to steering wheel

    • Fix the steering in the frame reference sketch

 

Upcoming Deadlines

  • - Upper steering architecture selected (is in talks with ergo and suspension)- Steering
  • - Bump steer design optimization - Steering
  • - Every single part has a CAD
  • - Version 1 of Upright design in CAD - Unsprung
  • - Finalize brakes and rotor config (Arav got us this data) - Unsprung
  • - Caliper and motor mount for Swingarm - Unsprung + Suspension
  • - Version 1 of Hub design in CAD - Unsprung
  • - Brake calipers and rotor size decided (Arav got us this data) - Unsprung

💨 Aeroshell:

Updates

  • Aerodynamics

    • some members(at least 2) got their sims done

  • Composites

    • all bb layups except 1

    • all daybreak prep done, pretty much ready to bond w/ frame whenever

    • Did first frame test pieces

    • Did one with a higher vol fraction which looks better (bc less excess resin) but i forgot to take pic

    • Sanded the fcf part a bit, not effective. takeaway: we need to get rid of layer lines in mold. solution, more sanding or acetone vapor stuff

      image-20241203-012523.png
    • michael and i cleaned out pickle

 

 

Week Plan

  • Aerodynamics

    • everyone needs to have an idea for the part they want to put on the shell, it needs to be able to put together as a final part on workday

  • Aeroshell(me)

    • need to define some architecture things by workday, flat topshell or not,

  • Composites

    • finish battery box, another metal sheet to be sanded, start making test coupons for nomex honeycomb frame panels, finalize test fixtures for panels, finalize test plans for demold and resin infusion

    • Also will be working w/ emech to finalize plans for composite enclosure and also testing abs acetone vapor stuff to use in composite enclosure and composite steering wheel

 

Upcoming Deadlines

  • Nov 20, 2024 - aerodynamics members have sims prepped
  • - Battery box layups + Kaden's test panel complete
  • - Daybreak shell prep complete and ready for shell to frame attachment
  • Dec 7, 2024 (Before workday) - Aerodynamics members know what part they want to put on the shell
  • Dec 7, 2024 (EOD) - Model of car is made around the frame, and it has all the parts that members have made

✅ New Action items

  • Ask members if they’re coming to workday
  • Ask Jessica about Digilent
  • Ask OB about trailer length
  • Talk to diyur

⤴ Decisions

    • No labels