2024 -2026 Timeline and Dependency Charts Planning

Purpose: develop a rough idea of a timeline for your system, including major goals, their dependencies, and when you want to accomplish them by

Aeroshell

Major Goals

Dependencies

Rough Timeline

Major Goals

Dependencies

Rough Timeline

Design shell

Fergo, what does the frame look like

Dynamics, how much space will wheels take/ turning radius etc, exposed suspension

Array - array size/config

  • Decide what the car will look like(3/4 wheel)

  • Design car in Solidworks: 12/14/24

  • Begin work on one half of car: 1/11/25

  • Finish that half: 5/3/25

  • Begin work on second half: 5/17/24

  • Finish full composite shell: 12/13/25

  • Completely finalized aeroshell: spring break '26

Demold bottom shell

 

Top shell layup complete

 

Bottom shell layup complete

 

Fergo/Structures

Major Goals

Dependencies

Rough Timeline

Major Goals

Dependencies

Rough Timeline

Frame welded

Frame validated and ordered

  • Driver dimensions taken

  • Seats molded

  • Frame Design drafted

  • Ergo Parts (pedal box, steering wheel, ballast box, etc.) drafted

  • Frame ordered

  • Frame welded

  • Ergo integrated onto frame

     

     

Pedal box assembled

Drivers set in stone, driver model created, pedal design validated and ordered

Chassis width decided

Dynamics geometry decided

Dynamics

Major Goals

Dependencies

Rough Timeline

Major Goals

Dependencies

Rough Timeline

Onboarding/Training

Recruitment

  • Training: 10/12/24

  • Preliminary Designs: 11/9/24

  • Final Designs Ideally: Before we leave for winter break

  • Final Designs FINAL: 2/15/25

  • Manufacturing Begins: 2/22/25

  • Manufacturing Finished: Before start of winter break of 2025

  • Integration starts depending on other systems

Trackwidth decided

 

Volumetric bounding box decided

 

 

 

Unsprung components assembled

 

Suspension components assembled

 

Electromechanical

Major Goals

Dependencies

Rough Timeline

Major Goals

Dependencies

Rough Timeline

Volumetric bounding box decided (New Car)

Frame/Dynamics - where battery can go, how much space there is

  • Training Finished - 10/12/24

  • Day Break Battery Architecure Finalized - Mid October

  • Day Break Enclosure design finalized (mounting, cooling) - Before Winter break

  • Day Break Battery Manufactured - End of Feb/Early March

  • New Battery Architecture + any new features Finalized - before winter break

  • New Battery Enclosure (with mounting and cooling) designed - End of March

  • New Car battery manufactured - Nov 25

  • New Car Battery/Electrical Testing - Dec 25 - Mar 26

  • New Car Top Level Layout Finalized - Mid October

New Battery finished/manufacture (New Car)

Electrical

Frame

New Cooling Finished (New Car)

Frame, Aeroshell, Battery - duct routing, exhaust/inlet placement

Possibly: Ergo, Dynamics, and Enclosures placements (in case of any interferences)

High level placement of enclosures/electrical hardware (New Car)

Electrical
Frame - locate hardware + sensors on car

Aeroshell - lights
Ergo - brake and accel

Battery Pack Module/Segment interfacing hardware/parts (Day Break)

Power Systems - new/old cells

BPS - how modules will be organized into segments

Battery Box manufactured (Day Break)

 

Driver cooling + motor controller design complete

Controls

Frame

Dynamics

Aeroshell