2024-09-10 Leads Meeting

 Date

Sep 10, 2024

 Participants

  • @Philip Bortolotti

 Goals

  • Should we even fix Daybreak?

  • Nathan’s talk with professor

  • Work needed to complete Daybreak

  • Timeline for Daybreak

 Discussion topics

Time

Item

Presenter

Notes

Time

Item

Presenter

Notes

8:07 - 8:15

Pros and Cons of continuing working on Daybreak

Philip

Pros:

  • The team spent time to create the car and it would be a waste not to finish

  • We can have new members take parts of the car and see a direct product

  • Data Acquisition

  • Scrutineering Practice

  • PR CR

  • Backup Car

Cons:

  • Money

  • Time

  • Take time away from Supernova (next car)

  • Leads management

image-20240911-012039.png ← Picture here

8:15 - 8:30

Nathan cosplays as keena

nathan

Keena:

  • Thinks all three teams have poor discipline

  • Car should 1. design, 2. manufacture, 3. test

  • Not spending enough time testing for the competition

  • Changing most of SRR after the process and not upholding the ideas

  • PLAN THIS OUT, please

  • Splitting our time between the past and future is hard

8:30 - 8:50

What work do we need to do

everyone

Weeks (Wk)

Aeroshell (Less than a month - 4 Wk):

  • Canopy Latch

  • Canopy Hinge

  • Shell to Frame

  • Shell to Shell

  • Lanyard placement

BPS:

  • Scrutineering board - 3 Wk

  • React to Battery changes

  • Fan board - 3 Wk

Controls:

  • Leaderboard rework

  • Motor controller figure out

  • Dashboard PCB

  • Purchase new lights

Data Acq:

  • Radios

Dynamics:

  • Dynamics: suspension and steering at the beginning and for the most part can be worked on separate

    • Wishbone elongate -

      • redesigning - two weeks

      • bearing inserts purchase after design changes to wishbone - two week wait time

      • manufacturing wishbones - waterjetting(?) = wait time

    • Steering -

      • dependent on suspension new geometry and wheelcutout interference

      • purchasing a new rack - waiting time

      • new longer tie rods update cad and manufacture, helicoiling

      • steering column and ujoints

    • steering mounts welding -

      • part of steering geom cad

      • then weld - midway through dynamics completion for testing

    • Shock Extender - last in suspension

      • do we need to redesign? - machine

    • Fix tabs welding (low key fergo job) - new tabs - last

Emech:

  • New Battery

  • 3D print new duct adapters

  • Rewire car bruh

Fergo:

  • Fix some welds

  • Steering wheel mounting fix

  • Brake Light sensor (x controls)

  • Fix Brake calipers

Power Gen:

  • Array test and general maintenance

    • Might have to do some lamination

  • Swap out mppt’s with newer commercial

Power Systems:

  • Redesign power board

  • Contactor Driver Revision

  • Battery PCB’s

8:50 - 8:56

 

 

Break

8:56 - 10ish

Timeline

Michael + everyone

 

image-20240911-111455.png
not pictured: motor being taken out :)

 

@Philip Bortolotti

 

 Action items

 Decisions

Related pages